COMPLETED PROJECTS

Goffstown, NH – Greggs Substation Rebuild
ANTICIPATED COMPLETION: Summer 2023

Working as a sub-contractor to Ciambro, RS Audley is performed the site work for the Greggs Falls Substation Rebuild in Goffstown, NH.

Seabrook, NH – Seabrook Seawall Repair – ANTICIPATED COMPLETION: Spring 2023

This project involves select demolition of existing appurtenances and installing new steel sheet pile bulkhead/cap outboard of the existing bulkhead. Internal steel wale and tieback extensions will be installed to tie into the existing tieback system.

Dunbarton, NH – Countryside Estates Subdivision – Completed in 2022

This project developed the old Countryside Golf Course into the Countryside Estates Subdivision.

Loudon-Canterbury, NH – Route 106 Widening
BID AMOUNT: $7,187,695.28 – ANTICIPATED COMPLETION: SEPTEMBER 2021

This project widened 3.5-mile segment of Route 106 to improve highway safety and mobility.

Hooksett, NH – I-93 Median Barrier 
BID AMOUNT: $696,435.50 – ANTICIPATED COMPLETION: Fall 2021

This project involved removing and upgrading the deficient median guardrail with concrete barrier along I-93 in Hooksett between the toll plaza and the I-293 split.

Bow, NH – NH Route 3A & Dunklee Road Intersection & Dunklee Road Bridge Rehabilitation
BID AMOUNT: $1,836,463.00 – ANTICIPATED COMPLETION: Summer 2021

This project will widen Route 3A and reconstruct the intersection with Dunklee Road. The project also realigns Dunklee Road and replaces the Dunklee Road bridge over Bow Bog Brook.

Derry/Londonderry, NH – I-93 Exit 4 Interchange
BID AMOUNT: $62,296,391.29 – ANTICIPATED COMPLETION: SEPTEMBER 2020

This project constructed 6 bridges, widened 5 miles of interstate, reconstructed 5 interstate ramps, and re-aligned NH Route 102 and Pillsbury Street.

Roxbury/Sullivan, NH – Reconstruction of Route 9
BID AMOUNT: $13,451,513.85  – COMPLETED FALL 2019

This project reconstructs 2.1 miles of NH Route 9 and replaces the NH Route 9 bridge over Otter Brook. This job will also construct major slope treatments along Route 9 and Bridge Rehabilitation work on the Centre Street Bridge over Otter Brook.

Manchester-Boston Regional Airport – Reconfiguration of TW P & U
BID AMOUNT: $9,604,198.50  COMPLETED FALL 2019

This project reconfigures Taxiways ‘P’ and ‘U’ along with the removal of Taxiway ‘A1’. Included in the scope of work is excavation, embankment-in-place, removal of pipes and structures, drainage installation, subbase course construction, basecourse construction, HMA paving, airfield lighting and signage, utility relocations, pavement markings, pavement grooving, and construction of a 14,000 SF retaining wall.

Windham/Derry, NH I-93 Widening/Reconstruction
BID AMOUNT: $49,419,914.55 – COMPLETED: SPRING 2019

This project involves widening and reconstructing 8 miles of highway and 4 bridges between Exit 3 and Kendall Pond Road on I-93 in Windham/Derry, NH. This project also includes a soundwall and pedestrian box culvert beneath the interstate.

Get In Touch

R.S. Audley, Inc.

1113 Route 3A
Bow, NH 03304

Follow Us