COMPLETED PROJECTS
ANTICIPATED COMPLETION: Summer 2023
Working as a sub-contractor to Ciambro, RS Audley is performed the site work for the Greggs Falls Substation Rebuild in Goffstown, NH.
This project involves select demolition of existing appurtenances and installing new steel sheet pile bulkhead/cap outboard of the existing bulkhead. Internal steel wale and tieback extensions will be installed to tie into the existing tieback system.
This project developed the old Countryside Golf Course into the Countryside Estates Subdivision.
BID AMOUNT: $7,187,695.28 – ANTICIPATED COMPLETION: SEPTEMBER 2021
This project widened 3.5-mile segment of Route 106 to improve highway safety and mobility.
BID AMOUNT: $696,435.50 – ANTICIPATED COMPLETION: Fall 2021
This project involved removing and upgrading the deficient median guardrail with concrete barrier along I-93 in Hooksett between the toll plaza and the I-293 split.
BID AMOUNT: $1,836,463.00 – ANTICIPATED COMPLETION: Summer 2021
This project will widen Route 3A and reconstruct the intersection with Dunklee Road. The project also realigns Dunklee Road and replaces the Dunklee Road bridge over Bow Bog Brook.
BID AMOUNT: $62,296,391.29 – ANTICIPATED COMPLETION: SEPTEMBER 2020
This project constructed 6 bridges, widened 5 miles of interstate, reconstructed 5 interstate ramps, and re-aligned NH Route 102 and Pillsbury Street.
BID AMOUNT: $13,451,513.85 – COMPLETED FALL 2019
This project reconstructs 2.1 miles of NH Route 9 and replaces the NH Route 9 bridge over Otter Brook. This job will also construct major slope treatments along Route 9 and Bridge Rehabilitation work on the Centre Street Bridge over Otter Brook.
BID AMOUNT: $9,604,198.50 COMPLETED FALL 2019
This project reconfigures Taxiways ‘P’ and ‘U’ along with the removal of Taxiway ‘A1’. Included in the scope of work is excavation, embankment-in-place, removal of pipes and structures, drainage installation, subbase course construction, basecourse construction, HMA paving, airfield lighting and signage, utility relocations, pavement markings, pavement grooving, and construction of a 14,000 SF retaining wall.
BID AMOUNT: $49,419,914.55 – COMPLETED: SPRING 2019
This project involves widening and reconstructing 8 miles of highway and 4 bridges between Exit 3 and Kendall Pond Road on I-93 in Windham/Derry, NH. This project also includes a soundwall and pedestrian box culvert beneath the interstate.
